Hi,
I faced an issue about the relation between RFQ, PO, and item requirement (SO) in project module. ias described in this hotfix "KB 3082857 Project item requirements do not update correct quantity when a PO is made by a Request for Quotation (RFQ)"
I have installed that hotfix and somehow it is not working. the issue still remains. What i do when I installed it :
1. Use Development environment
2. Turn off the AOS services
3. Run the axupdate.exe (install result was a success)
4. Restart the AOS
5. Start the Application
6. Generate Incremental CIL
7. Compare the sys layer and syp layer (the difference is there)
8. For double check. I also compare the syp in my development with the one on LCS changelog. it is the same. steps 7 and 8 means the hotfix new code is integrated to my AOS
9. Issue still remains. so I restart the Development Server
10. Issue still remains
Do you guys have any suggestion about this ? or this hotfix simply does not take effect ?
BR,
Satria